Study period: January 2024 – March 2026
Dataset size: 45 determined applications (processing duration analysed)
Wards: Withington, Fallowfield, Old Moat
Focus: Determination timelines by application type, outcome, and ward
Source: Manchester City Council Public Access Planning Portal
This article forms part of the South Manchester HMO Planning Intelligence series, a ward-level analysis of HMO planning activity across 14 Manchester wards covering 100 applications.
Key Findings
56 days was the modal determination period across the dataset — consistent with the standard 8-week planning target. Mean processing time: 58.8 days across 45 determined applications.
Certificate refusals produced the tightest clustering: all 8 determined within a 5-day window (52–57 days, standard deviation 1.7 days). No refused application exceeded 57 days. Duration outliers were confined to approval cases — the two longest determinations (161 and 134 days) were both approvals.
Determination Timelines
Determination timelines define the period between application validation and decision. This article documents processing duration across 45 determined applications in the dataset, examining variation by application type, outcome, and individual case.
Data Scope
This analysis examines processing duration data from 47 HMO planning applications submitted between 2024 and 2026 across Withington, Fallowfield, and Old Moat.
Of 45 applications submitted, 43 were formally determined and 2 were withdrawn prior to decision. Approval and refusal rates are calculated against determined applications (n=43) unless otherwise stated. Processing duration is measured in holding days: the period between validation date and decision date as recorded in the planning portal.
Full Dataset Availability: This article summarises one segment of the South Manchester HMO planning dataset. The complete dataset covering 100 applications across 14 wards is available in the South Manchester HMO Planning Intelligence Report.
Dataset-Wide Duration Overview
Mean processing time: 58.8 days
Median processing time: 56.0 days
Minimum: 38 days
Maximum: 161 days
Standard deviation: 22.6 days
The standard 8-week (56-day) target appeared as the modal determination across the dataset. 56 days was the single most frequently recorded processing time, appearing in multiple determinations across all three wards and both application types.
Certificate Application Durations
Approved Certificates (n=31)
Mean: 58.2 days | Median: 56.0 days | Range: 38–161 days | SD: 20.5 days
The 161-day outlier (44 Lombard Grove, Old Moat) represents the longest determination in the dataset. This application was a Certificate of Lawful Development Proposed — the only LP application in the dataset. All other Certificate applications were Existing use (LE) applications. The LP application’s extended determination period distinguishes it from the LE pattern.
Excluding the 161-day outlier, approved Certificate determinations ranged from 38 to 79 days with a mean of 55.5 days — closely aligned with the 56-day modal figure.
Refused Certificates (n=8)
Mean: 54.9 days | Median: 55.5 days | Range: 52–57 days | SD: 1.7 days
Key Finding
Certificate refusals produced the tightest duration clustering in the dataset. All 8 refusals were determined within a 5-day window (52–57 days). The standard deviation of 1.7 days indicates near-uniform processing time across refused Certificate applications.
Certificate refusals were determined marginally faster on average than Certificate approvals (54.9 days vs 58.2 days). The single withdrawn Certificate application recorded 13 holding days before withdrawal — the shortest active period in the dataset.
Full Application Durations
Approved Full Application (n=1)
Processing time: 134 days (8 Beech Grove, Withington)
The single approved Full Application was determined in 134 days — 78 days beyond the 56-day modal figure and the second-longest determination in the dataset.
Refused Full Applications (n=5)
Mean: 54.0 days | Median: 56.0 days | Range: 47–56 days | SD: 3.9 days
Full Application refusals processed within a similarly tight window to Certificate refusals (54.0 days mean vs 54.9 days mean). Four of five Full Application refusals were determined in exactly 56 days or fewer. The single withdrawn Full Application recorded 43 holding days before withdrawal.
Approval vs Refusal Duration Comparison
| Outcome | Application Type | n | Mean (days) | Median (days) | Range |
|---|---|---|---|---|---|
| Approved | Certificate | 31 | 58.2 | 56.0 | 38–161 |
| Refused | Certificate | 8 | 54.9 | 55.5 | 52–57 |
| Approved | Full Application | 1 | 134.0 | 134.0 | 134 |
| Refused | Full Application | 5 | 54.0 | 56.0 | 47–56 |
Refusals processed marginally faster than approvals for Certificate applications (54.9 vs 58.2 days mean). The single Full Application approval processed substantially longer than Full Application refusals (134 days vs 54.0 days mean).
The 56-Day Modal Pattern
56 days appeared as the most frequently recorded determination period across the dataset, spanning all three wards, both application types, and both approved and refused outcomes. The concentration of determinations at or near 56 days is consistent with the standard 8-week planning determination target.
No refused application in this dataset exceeded 57 days.
Duration Outliers
Longest: 161 days — 44 Lombard Grove, Old Moat (Certificate Lawful Development Proposed). The only LP application. Approved.
Second longest: 134 days — 8 Beech Grove, Withington (Full Application). The only Full Application approval in the dataset.
Third longest: 79 days — Flat 1, 52 Central Road, Old Moat (Certificate Existing). Approved.
Shortest: 38 days — 149 Braemar Road, Fallowfield (Certificate Existing). Approved. 18 days below the modal figure.
Ward-Level Duration Patterns
| Ward | Determined | Mean (days) | Median (days) | Range | Mean excl. outlier |
|---|---|---|---|---|---|
| Withington | 18 | 58.3 | 56.0 | 43–134 | 54.0 |
| Fallowfield | 13 | 53.8 | 56.0 | 38–70 | — |
| Old Moat | 14 | 64.2 | 56.0 | 47–161 | 56.8 |
Ward-level means were influenced by outliers: the 161-day LP application in Old Moat and the 134-day Full Application approval in Withington. Excluding these two cases, all three wards recorded means within 2 days of the 56-day modal figure. Fallowfield recorded the lowest mean processing time and the tightest range.
Repeat Submission Intervals
Egerton Road, Withington: 132 days (refusal to second approval)
Landcross Road, Fallowfield: 98 days (refusal to second approval)
A third repeat submission street (Furness Road, Fallowfield) recorded a refusal and subsequent approval but complete interval data is not available for that case. The repeat submission intervals represent the total elapsed period from initial refusal to final approval — encompassing evidence gathering, resubmission preparation, and second determination processing. Duration variation was concentrated in a small number of approval cases, while refusal determinations clustered tightly around the statutory target window.
Conclusion
Processing durations across 45 determined applications clustered around the standard 8-week (56-day) target. 56 days was the modal determination period, appearing across all three wards, both application types, and both approved and refused outcomes.
Certificate refusals produced the tightest duration clustering: all 8 were determined within a 5-day window (52–57 days, standard deviation 1.7 days). Certificate approvals showed wider variation (38–161 days, standard deviation 20.5 days), driven primarily by one LP outlier (161 days).
The single Full Application approval (8 Beech Grove) required 134 days — the second-longest determination in the dataset. All five Full Application refusals were determined within 56 days or fewer.
No refused application exceeded 57 days. Applications resulting in approval showed greater duration variation than those resulting in refusal. Excluding the two outlier cases, all three wards recorded means within 2 days of the 56-day modal figure.
About This Research
This article forms part of the South Manchester HMO Planning Intelligence series, a structured analysis of HMO-related planning applications submitted to Manchester City Council between January 2024 and March 2026. The dataset currently covers 100 applications across 14 South Manchester wards, examining approval rates, refusal patterns, application types, submission channels, and determination timelines. All analysis is based on publicly available planning records.
Access the Complete Analysis
The South Manchester HMO Planning Intelligence Report provides full processing duration data for all 45 determined applications by address, validation and decision dates, repeat submission interval tracking, duration breakdown by agent, ward, and application type, and timeline sequencing across the full 2024–2026 period.
Also available as individual ward reports:
Withington — £39 · Fallowfield — £39 · Old Moat — £39